Meeting #199

Updated by André Neto over 9 years ago

h1. Sprint planning

*Date of the meeting:* 24/08/2015
*Sprint objective:* Fourth release of MARTe with support for logging and AnyType. Some refactoring of L0Portability namespacing and memory management to also be included.
*Backlog items:* #169, #203, #196, #204, #194, #201, #202, #182, #195

h1. Sprint review

Almost all the user-stories were successfully completed. Only Windows porting remains to be addressed (see Technical debt below).

h1. Sprint retrospective

* Things that the team should start doing


Nothing to report.

* Things that the team should stop doing


Nothing to report.

* Things that the team should continue doing


Nothing to report.

h1. Technical debt

Non-completed user-stories: #169

h1. Backlog review (restimation, reprioritization, weighting)

The sprint was successful, with the exception of #169 which requires the macros and makefiles to be updated against the current strategy.