h1. Sprint planning

*Date of the meeting:* 29/09/2015
*Sprint objective:* Sixth release of MARTe aimed at finishing the introspection base infrastructure and implementing streams support
*Backlog items:* #169, #188, #235, #236, #237, #238, #239, #240

h1. Sprint review

The following issues and concerns were discussed by the team during the sprint:

* Non-tested functions of #240 to be reported in the Q&A audit report.

h1. Sprint retrospective

* Things that the team should start doing

* Things that the team should stop doing

* Things that the team should continue doing

h1. Technical debt

h1. Backlog review (restimation, reprioritization, weighting)