Meeting #298
Updated by André Neto about 9 years ago
h1. Sprint planning
*Date of the meeting:* --/--/2016
*Sprint objective:* Eleventh release of MARTe aimed at finalising the introspection.
*Backlog items:* #188, #264, #295, #296
h1. Sprint review
Several files were found not be properly linted. Apparently the header files also have to be included in the lint configuration file.
h1. Sprint retrospective
* Things that the team should start doing
Nothing new to report.
* Things that the team should stop doing
Nothing new to report.
* Things that the team should continue doing
Nothing new to report.
h1. Technical debt
Non-completed user-stories:
All user-stories completed!
h1. Backlog review (restimation, reprioritization, weighting)
No backlog pending. The current version compiles in Windows and Linux.
*Date of the meeting:* --/--/2016
*Sprint objective:* Eleventh release of MARTe aimed at finalising the introspection.
*Backlog items:* #188, #264, #295, #296
h1. Sprint review
Several files were found not be properly linted. Apparently the header files also have to be included in the lint configuration file.
h1. Sprint retrospective
* Things that the team should start doing
Nothing new to report.
* Things that the team should stop doing
Nothing new to report.
* Things that the team should continue doing
Nothing new to report.
h1. Technical debt
Non-completed user-stories:
All user-stories completed!
h1. Backlog review (restimation, reprioritization, weighting)
No backlog pending. The current version compiles in Windows and Linux.