Sprint planning¶
Date of the meeting: 06/04/2016
Sprint objective: Twelfth release of MARTe aimed at implementing the GAM and message infrastructures.
Backlog items: #22, #301, #305, #306, #307, #308, #309, #310, #313, #200, #183, #189, #304
Sprint review¶
Sprint retrospective¶
- Things that the team should start doing
- Things that the team should stop doing
- Things that the team should continue doing
Technical debt¶
Non-completed user-stories:
Code review non-conformities: See #303
Unit test non-conformities: See #303
Backlog review (restimation, reprioritization, weighting)¶
History
#1 Updated by Ivan Herrero over 8 years ago
- Description updated (diff)
#2 Updated by Ivan Herrero over 8 years ago
- Description updated (diff)
#3 Updated by Ivan Herrero over 8 years ago
- Description updated (diff)
#4 Updated by André Neto about 8 years ago
- Status changed from New to Closed