Meeting #302
Updated by Ivan Herrero over 8 years ago
h1. Sprint planning
*Date of the meeting:* 06/04/2016
*Sprint objective:* Twelfth release of MARTe aimed at implementing the GAM and message infrastructures.
*Backlog items:* #22, #301, #305, #306, #307, #308, #309, #310, #313, #200, #183, #189, #304
h1. Sprint review
h1. Sprint retrospective
* Things that the team should start doing
* Things that the team should stop doing
* Things that the team should continue doing
h1. Technical debt
Non-completed user-stories:
Code review non-conformities: See #303
Unit test non-conformities: See #303
h1. Backlog review (restimation, reprioritization, weighting)
*Date of the meeting:* 06/04/2016
*Sprint objective:* Twelfth release of MARTe aimed at implementing the GAM and message infrastructures.
*Backlog items:* #22, #301, #305, #306, #307, #308, #309, #310, #313, #200, #183, #189, #304
h1. Sprint review
h1. Sprint retrospective
* Things that the team should start doing
* Things that the team should stop doing
* Things that the team should continue doing
h1. Technical debt
Non-completed user-stories:
Code review non-conformities: See #303
Unit test non-conformities: See #303
h1. Backlog review (restimation, reprioritization, weighting)